Bumbuna II

Bumbuna II

STATUS: Approved investment

Publication date: 16 November 2018
Region: Western Africa
Country: Sierra Leone
Sector: Hydropower
Total ElectriFI financing: 3.5 M
Environmental and Social Category*: A

*(A) high risk, (B+) medium high risk, (B) medium risk or (C) low risk

Brief description of the client and project

Joule Africa is in late stage development of the 143 MW Bumbuna II hydro project in Sierra Leone. The project comprises a dam resulting in a new reservoir at the Yiben area and the extension of  the existing Bumbuna I hydropower site, 32 kms downstream. Once completed, BBII is estimated to generate 1,062 GWh per annum and will provide a minimum guaranteed 80MW power throughout the year. It will connect to the national grid and sell its output under a 25yr PPA with national utility EDSA.

Funding objective

ElectriFI will provide a USD 3.5mln convertible loan to Joule Africa in order to finance 50% of the external final hurdle development expenses aimed at reaching financial close of the project

Why ElectriFI wants to fund this project.

The Bumbuna II project is crucial for the GoSL to stimulate its energy sector and support its economic growth strategy. Bumbuna will double the national generation capacity; indirectly enable investments in transmission and distribution network; and allow GoSL to show it is capable of managing large international infrastructure investments such as this. Joule Africa has demonstrated itself to be a professional, dedicated project developer, taking seriously its role, in particular by ensuring the adequacy of capacity in GoSL and by ensuring net gains to the communities and the environment affected by the Project.

Environmental and social rationaleWhich IFC PSs are triggered and the rationale behind it.

The Project is an environmental and social risk category A according to EDFI MC. The main environmental and social risks of this Project are related to (i) the impact on the Biodiversity (Critical and Natural habitat) (ii) impact on local communities – circa 3500 persons to be physically and economically impacted and (iii) general EHS management during Construction Phase.

All IFC Performance Standards are applicable with the exception of IFC PS7 on Indigenous People. The Environmental and Social Impact Assessment did not identify any people or groups of people qualifying under the definition of Indigenous People. The impacts are mitigated through dedicated mitigation plans and activities.

Disclaimer

The information as disclosed is indicative and provided on an “as-is/as available” basis for general informational purposes only and should not be construed as financial, legal or investment advice, nor as a commitment or an offer to arrange or provide any financing. The final decision to provide financing is subject to the terms and conditions of ElectriFI in its sole and absolute discretion.

In case of questions

This approved investment is online for 30 days. In case of questions, please contact info@edfimc.eu.